Grid project Beznau – Birr

Swissgrid is expanding the existing line between Beznau and Birr to 380 kV. A 1.3-kilometre section of the line at «Gäbihübel» near Bözberg/Riniken will be underground in future. The 220 kV line between Rüfenach and Habsburg will be dismantled.

Your contact for this grid project

Jan Schenk
Jan Schenk

Phone +41 58 580 21 11
info@swissgrid.ch

380 kV line
380 kV line
380 kV underground cabling
380 kV underground cabling
Dismantling
Dismantling
Existing line
Existing line
Substation
Substation

Overview

By increasing the voltage between Beznau (AG) and Mettlen (LU) from 220 to 380 kilovolts, Swissgrid is securing the energy distribution and security of supply in the metropolitan area of Zurich, Central Switzerland and the Swiss Central Plateau. The new construction of the approx. 6.5-kilometre Rüfenach – Habsburg section is the last part of the line between Beznau and Birr that has not yet been expanded.

Partial cabling at «Gäbihübel»

The project includes a first for Swissgrid: At Gäbihübel near Bözberg/Riniken, Swissgrid is laying a long section of an extra-high-voltage line underground for the first time. Transition structures will be built at both ends of the 1.3-kilometre section in order to connect the underground cable and overhead line. 5.2 kilometres of new overhead lines connect the underground cabled section to the route of the current line.

Easing the burden on the landscape and residential areas

After the cabling at Gäbihübel is commissioned, the entire overhead line between Rüfenach and Habsburg will be dismantled. As a result, the burden on the residential areas of Neu-Riniken and Hafen will be noticeably eased. Swissgrid considered the landscape as much as possible when positioning the two transition structures and the new section of overhead line.

A shop window for research and the public

At «Gäbihübel», the effects that cabling a long section of extra-high-voltage line has on the landscape and environment, the costs that result from this and the challenges presented in construction, operation and maintenance, will be visible for the first time. Swissgrid will provide scientific support for the project.

The costs for the entire project amount to around CHF 34 million.


Project

The project consists of the 1.3-km cable route, the northern and southern transition structures and 5.2 km of overhead line connections from pylon 20 in Rüfenach to pylon 30 in Krähtal and to the northern transition structure, as well as from the southern transition structure from pylon 32 in Villnachern to pylon 237 in Habsburg.

New construction of the extra-high-voltage line between Rüfenach (pylon 20) and Habsburg (pylon 237) with partial underground cabling at «Gäbihübel»
New construction of the extra-high-voltage line between Rüfenach (pylon 20) and Habsburg (pylon 237) with partial underground cabling at «Gäbihübel»
Visualisierung Teilverkabelung «Gäbihübel»
Partial cabling «Gäbihübel» (in German)

Carefully positioned transition structures

To connect the underground cabling with the overhead line connections, transition structures will be built to the north and to the south of «Gäbihübel». They each require an area the size of an ice hockey rink and are around 25 metres high.

Schematic representation of a transition structure
Schematic representation of a transition structure

Swissgrid optimised the locations of the two transition structures during the course of the project. The northern transition structure in the «Pfaffenfirst» region has been positioned so that it is concealed as much as possible by the surrounding forest. The forest clearance and reforestation work required for this has already been completed. The southern transition structure will be built in the «Untere Stockacher» region, directly below the SBB Bözberg route, in order to protect the scenery as much as possible and to combine the emissions from rail and transmission line infrastructures.

Connection to the cable route
1/22: Connection to the cable route
 Installation of the transition structure
2/22: Installation of the transition structure
Installation of the transition structure
3/22: Installation of the transition structure
 Installation of the transition structure
4/22: Installation of the transition structure
Installation of the transition structure
5/22: Installation of the transition structure
Installation of the transition structure
6/22: Installation of the transition structure
Unlodading  of the transition structure
7/22: Unlodading of the transition structure
Ready for the installation of the transition structure
8/22: Ready for the installation of the transition structure
Übergangsbauwerke: Fertigung der Abspannportale
9/22: Transitional structures: Construction of the portal pylons
Transitional structures: Construction of the portal pylons
10/22: Transitional structures: Construction of the portal pylons
Übergangsbauwerke: Fertigung der Abspannportale
11/22: Transitional structures: Construction of the portal pylons
Southern transitional structure: Construction of the last ceiling section
12/22: Southern transitional structure: Construction of the last ceiling section
Southern transitional structure: Cable outlet to the portal pylon
13/22: Southern transitional structure: Cable outlet to the portal pylon
Southern transitional structure: Construction of supporting pillars and floor
14/22: Southern transitional structure: Construction of supporting pillars and floor
Transition structure south: building of the side walls
15/22: Transition structure south: building of the side walls
Transition structure south: concreting of the base plate
16/22: Transition structure south: concreting of the base plate
Transition structure south: reinforcement of the base plate
17/22: Transition structure south: reinforcement of the base plate
Northern transitional structure: Reinforcement of the ceiling
18/22: Northern transitional structure: Reinforcement of the ceiling
Northern transitional structure: Concreting the foundation slab, putting up the side walls
19/22: Northern transitional structure: Concreting the foundation slab, putting up the side walls
Transition structure north: transition of cable pipeline
20/22: Transition structure north: transition of cable pipeline
Transition structure north: excavation
21/22: Transition structure north: excavation
North transition structure
22/22: The completed north transition structure

Laying the underground cable

For the excavation and construction works required to lay the high-voltage line under the ground, a 25-metre-wide route must be created along the length of the cable. The approx. 5-metre-wide cable trench will be excavated in the centre of this. To do this, around 30,000 m3 of excavated material will be added and removed in Bözberg and around 25,000 m3 in Villnachern. Then the two 1.5-metre-wide conduit blocks will be recessed into the ground. In a subsequent step, six cables will be installed in each conduit block. This is a logistically challenging task, as underground cables are significantly heavier than overhead lines as a result of their much thicker insulation. Finally, the two conduit blocks will be covered with around one metre of earth. The route will then be renaturalised, apart from a 4.5-metre-wide strip over the two conduit blocks.

Schematic representation of the cable trench during the construction phase
Schematic representation of the cable trench during the construction phase
Spreading of humus / restoration of the original state
1/7: Spreading of humus / restoration of the original state
Filling in the cable trench
2/7: Filling in the cable trench
Covering of the conduit blocks
3/7: Covering of the conduit blocks
Cementing of the cable conduits
4/7: Cementing of the cable conduits
Installation of the cable conduits
5/7: Installation of the cable conduits
Installation of the cable conduits
6/7: Installation of the cable conduits
Excavation of the cable pipeline
7/7: Excavation of the cable pipeline

Installation of the underground cable

In summer 2019, the 380-kilovolt underground cables manufactured by Brugg Cables were installed in the cable conduits. Each of the twelve cables weighs around 40 tonnes together with the cable reel. In July and August 2020, the cable reels were brought from Brugg to the northern transition structure by heavy load transporter in twelve trips. Then they were unloaded and installed in the cable conduits.

Installation of the cables
1/19: Installation of the cables
Installation of the cables
2/19: Installation of the cables
Installation of the cables
3/19: Installation of the cables
Installation of the cables
4/19: Installation of the cables
Installation of the cables
5/19: Installation of the cables
Installation of the cables
6/19: Installation of the cables
Installation of the cables
7/19: Installation of the cables
Installation of the cables
8/19: Installation of the cables
Installation of the cables
9/19: Installation of the cables
Installation of the cables
10/19: Installation of the cables
40-ton cable reel
11/19: Impressive dimensions: One of the twelve 40-ton cable reels in a hall of Brugg Cables ready for transportation to Gäbihübel
Cable production, part 1: Production of the aluminium conductor segments
12/19: Cable production, part 1: Production of the aluminium conductor segments
Cable production, part 2: Stranding of the 5 aluminium conductor segments
13/19: Cable production, part 2: Stranding of the 5 aluminium conductor segments
Cable production, part 3: Semiconductor coating and insulation
14/19: Cable production, part 3: Semiconductor coating and insulation
Cable production, part 4: Sheathing with absorbent fleece
15/19: Cable production, part 4: Sheathing with absorbent fleece
Cable production, part 5: Attachment of the copper wire shielding
16/19: Cable production, part 5: Attachment of the copper wire shielding
Cable production, part 6: Mechanical protective coatings I
17/19: Cable production, part 6: Mechanical protective coatings I
Cable production, part 7: Mechanical protective coatings II
18/19: Cable production, part 7: Mechanical protective coatings II
Cable production, part 8: Reeling of the finished cables
19/19: Cable production, part 8: Reeling of the finished cables

Facts and figures relating to the partial cabling at «Gäbihübel»

Overall project6.5 km line, consisting of 5.2 km overhead line and 1.3 km underground cable
Voltage level380 and 220 kV
Number of underground cables12
Underground cable weight21 kg per metre
Total underground cable weightaround 380 tons
Number of new pylons14
Number of dismantled pylons19
Height of the pylons47 to 80 metres (pylon 34, 35, 36 in Villnachern)
BuilderSwissgrid Ltd
Site managementGähler und Partner AG
General civil engineering contractorERNE AG Bauunternehmung
Cable supplierBrugg Cables

Construction of the overhead line connections

In parallel with the laying of the underground cable, the new sections of overhead line (5.2 kilometres in total), will be constructed. These connect the underground portion at «Gäbihübel» to the route of the existing overhead line. For this purpose, a total of ten new pylons will be constructed between pylon 20 at Rüfenach and the northern transition structure. Four new pylons will be constructed between the southern transition structure and pylon 237 at Habsburg. When planning the new overhead lines, Swissgrid attempted to find solutions that disturb the landscape as little as possible.

Installation of pulling line
1/11: Installation of pulling line
Installation of pulling line
2/11: Installation of pulling line
Installation of pulling line
3/11: Installation of pulling line
Retraction of auxiliary rope
4/11: Retraction of auxiliary rope
Installation of pulling line
5/11: Installation of pulling line
Installation of pulling line
6/11: Installation of pulling line
Installation of pulling line
7/11: Installation of pulling line
Installation of conductor
8/11: Installation of conductor
Installation of conductor
9/11: Installation of conductor
Installation of conductor
10/11: Installation of conductor
Installation of conductor
11/11: Installation of conductor

Dismantling previous overhead lines

The current 220 kV overhead line runs between Rüfenach and Habsburg, in part directly over the residential area (Neu-Riniken) or in its immediate vicinity (Hafen in the municipality of Bözberg). After the new line is commissioned, this overhead line is expected to be dismantled by the end of 2020. This will noticeably relieve the burden on the residential areas.

Pylon disassembly in Riniken
1/2: Pylon disassembly in Riniken
Pylon disassembly in Riniken
2/2: Pylon disassembly in Riniken

Schedule

Construction work at Gäbihübel officially began with the ground-breaking ceremony on 23 August 2018. The construction of transition structures, the conduit block and overhead line connections was completed in mid-2020. The new extra-high voltage line has been in service ever since. The dismantling of the existing overhead line will be completed by the end of 2020.

Project planning under optimum circumstances
Project planning under optimum circumstances

A project with an eventful pre-history

Initial plans to increase the voltage of the Beznau – Birr line to 380 kilovolts go back to the 1980s. In 1996 most of the overhead line sections were approved and built. In 2011, the Federal Supreme Court decided that a partial cabling project was to be developed at «Gäbihübel». In 2013, Swissgrid, now responsible for the transmission network, submitted a partial cabling project to the Swiss Federal Office of Energy (SFOE). In July 2016, it gave the green light.


People & environment

Landscape

Swissgrid will implement the most landscape-friendly line route possible when constructing the Gäbihübel partial underground cabling. Different versions and combinations of the cable route, locations of the transitional structures and the overhead line connections were reviewed. For example, the original position of the northern transitional structure was optimised so that it is concealed by the forest wherever possible. The overhead line connections are sympathetic to the landscape by blending in with the forest skyline.

Electromagnetic fields

An underground line causes electric and magnetic fields just like an overhead line. While electric fields are intercepted by the shielding in the cable, magnetic fields are generated externally. The spatial expansion of the magnetic fields is lower than for overhead lines, but the strength directly over the underground cable is much higher than under an overhead line. The limit of 1 microtesla is complied with from a distance of 6 – 8 metres to the line axis of the underground cable, while the corresponding distance for the overhead line is about 60 – 80 metres.

Soil and nature

The «Gäbihübel» partial underground cabling project will allow important knowledge to be gained on the underground cabling of extra-high-voltage lines. Swissgrid is therefore developing a scientific programme in consultation with the competent authorities and departments. The aim is to check the assumptions that were made for the dimensioning of the underground line and involves recording the underground line's impact on the soil. A comparison of the measurements with the calculations allows conclusions to be drawn about the reliability of the assumptions made.

In particular, the following points will be analysed during operation:

  • The temperature behaviour of the cable conductors under various operating conditions
  • The temperature profile in the soil in the immediate vicinity and the wider area about 20 metres from the conduit block under various operating conditions
  • The magnetic fields at different line loads

In the blog article «Soil is a precious resource», you will find detailed information on the impact of the underground cable on the soil and the environment.

Measuring station
Measuring stations monitor the underground cable

Forestry work

Permanent forest clearance (about 4,000 m²) was carried out for the northern transitional structure, opposite the garage on Bözbergstrasse as well as for the pylon locations. Temporary forest clearance was executed at the location for the northern transitional structure and for the pylon construction sites in the forest (about 17,000 m²). The forestry work was carried out in early 2018. The reforestation activities for the permanent forest clearance areas will take place in Linn, in the municipality of Bözberg, and in the areas in which pylons are removed. In Riniken, deforestation activities are necessary along the line route, since the overhead line is kept low. Small trees and shrubs will regrow in this area (maximum height of 12 m). In Villnachern, the conductors cross the riverside forest.


Impressions

Tunnelling beneath the SBB line
1/12: Tunnelling beneath the SBB line
Tunnelling beneath the SBB line
2/12: Tunnelling beneath the SBB line
Tunnelling beneath the SBB line
3/12: Tunnelling beneath the SBB line
Tunnelling beneath Bözbergstrasse
4/12: Tunnelling beneath Bözbergstrasse
Tunnelling beneath Bözbergstrasse
5/12: Tunnelling beneath Bözbergstrasse
Tunnelling beneath the SBB line
6/12: Tunnelling beneath the SBB line
Tunnelling beneath the SBB line
7/12: Tunnelling beneath the SBB line
Tunnelling beneath the SBB line
8/12: Tunnelling beneath the SBB line
Cable conduits before being welded together
9/12: Cable conduits before being welded together
Cable conduits before being welded together
10/12: Cable conduits before being welded together
Cable conduits
11/12: Cable conduits
Kabelschutzrohre
12/12: Cable conduits

Downloads


Grid news

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.