Grid project Innertkirchen – Mettlen

The 61-kilometre line section between Innertkirchen and Mettlen is to be replaced and upgraded from 220 to 380 kilovolts. The Swiss Federal Office of Energy decided on the Glaubenberg planning territory at the end of 2022. Swissgrid will now devise suggestions for corridors within the planning territory.

Your contact for this grid project

Sandra Bläuer
Sandra Bläuer

Phone +41 58 580 21 11
info@swissgrid.ch

380 kV line
380 kV line
220 kV line
220 kV line
Existing line
Existing line
Substation
Substation
Planning area
Planning area

Overview

  • Most of the line between Innertkirchen and Mettlen is over 70 years old and needs to be brought in line with the current state of the art.
  • At the same time, the line will be upgraded from today's 220 kilovolts to 380 kilovolts. This is necessary to ensure the transportation of the growing volume of electricity generated by the Oberhasli power plants and the hydroelectric power plants in Valais and Ticino to the Swiss Central Plateau.
  • In mid-2021, Swissgrid applied to the Swiss Federal Office of Energy (SFOE) to establish a planning territory between Innertkirchen and Mettlen. Planning territories are geographic areas within which a planning corridor, including transmission technology (underground cable, overhead line or combined options), can then be chosen at a subsequent stage of the project.
  • Swissgrid examined three possible planning territories: the Glaubenberg planning territory near the existing line as well as the Pilatus (through the Sarneraa Valley) and Entlebuch (via Sörenberg and Entlebuch) planning territories.
  • Each of the submitted options has certain pros and cons. From Swissgrid’s perspective, the Glaubenberg planning territory is the best option.
  • The SFOE decided on the Glaubenberg planning territory at the end of 2022. Swissgrid will now devise suggestions for corridors within the planning territory.
  • The Federal Council is expected to define the planning corridor and the transmission technology (underground cable, overhead line or a combined solution) in autumn 2025.

Project

Current situation

Most of the 61-kilometre extra-high-voltage line between Innertkirchen and Mettlen is over 70 years old and needs to be replaced. At the same time, the line voltage will be upgraded from the existing 220 kV to 380 kV along its entire length. This upgrade is an important project within Swissgrid’s implementation of «Strategic Grid 2025».

Why the project is necessary

Expanding the amount of electricity produced from hydropower is a central pillar of the Energy Strategy 2050. The increase in capacity between Innertkirchen and Mettlen is necessary to be able to transport the growing volume of electricity generated by the Oberhasli power plants and the Valais and Ticino hydroelectric power plants to the Swiss Central Plateau. Distributing energy flows along several north-south axes also increases grid stability. The Innertkirchen – Mettlen grid project therefore not only supports the expansion of renewable hydropower, it also ensures Switzerland’s security of supply.

The existing extra-high-voltage line between Innertkirchen and Mettlen leads over the Glaubenberg Pass.
The existing extra-high-voltage line between Innertkirchen and Mettlen leads over the Glaubenberg Pass.

Three possible planning territories

In mid-2021, Swissgrid applied to the Swiss Federal Office of Energy to establish a planning territory between Innertkirchen and Mettlen in the federal government’s sectoral plan for transmission lines. Planning territories are geographic areas within which a planning corridor, including transmission technology (underground cable, overhead line or combined options), can then be chosen at a subsequent stage of the project. To this end, Swissgrid examined three partly overlapping planning territories.

Overview of the three planning territories
Overview of the three planning territories
  • Glaubenberg planning territory
    This planning territory largely follows the existing 220 kV line and leads from Innertkirchen via Giswil and Glaubenberg to Malters and then on towards Mettlen. The greatest challenge of this option is the «Glaubenberg» flysch moor landscape. No overhead lines or underground cables installed using open trenching techniques are permitted in this landscape of national importance. Swissgrid therefore proposes to tunnel under Glaubenberg.
  • Pilatus planning territory
    The second option leads from Giswil through the Sarneraa Valley and then west or east of Pilatus to Littau and Mettlen. The main challenges presented by this option are the large settlement areas (Giswil, Sarnen, Alpnach, Hergiswil and Kriens), the scattered settlements, and the limitations imposed by the obstacles of the Kägiswil, Alpnach and Buochs airfields and the nationally protected Pilatus region.
  • Entlebuch planning territory
    As a third alternative, a planning territory could lead west from Giswil through Entlebuch to Mettlen. This option crosses through the UNESCO Entlebuch biosphere reserve and is much longer than the two other evaluated planning territories.

The Swiss Federal Office of Energy has decided on the Glaubenberg planning territory

Both of the submitted variants have specific advantages and disadvantages with respect to regional planning, the environment, technology and economic viability. The monitoring group of the Swiss Federal Office of Energy (SFOE) believes that the Glaubenberg planning territory is the best option. Firstly, it touches fewer settlement areas and involves fewer obstacles than the other options. Secondly, it is much shorter than the planning territory via Entlebuch and so has less of an impact on the ground, the natural environment and the landscape, requires less construction material and has lower energy losses and costs. At the end of 2022, the SFOE therefore decided on the Glaubenberg planning territory, with minor adjustments in relation to the variant submitted by Swissgrid.

At the end of 2022, the SFOE decided on the Glaubenberg planning territory, in particular because it touches fewer settlement areas, is short and direct, and has a lower environmental impact.
At the end of 2022, the SFOE decided on the Glaubenberg planning territory, in particular because it touches fewer settlement areas, is short and direct, and has a lower environmental impact.

Two sections are considered separately

The section between Mettlen and Hellbühl (Littau) is considered separately. It was upgraded to 380 kV in 1990, but is currently operating at just 220 kV. The Innertkirchen – Mettlen and Bickigen – Mettlen lines approach one another to the west of Rothenburg, from where they are bundled in the section to Mettlen. With this in mind, it makes sense to consider both lines together in this section in order to provide permanent relief for the settlement area. Swissgrid will therefore review the line routing in this area as part of the planned Bickigen – Mettlen line renovation. The line lead-in for the Innertkirchen substation will be considered separately within the Innertkirchen – Mettlen sectoral plan process: two additional transmission lines run parallel to the Innertkirchen – Mettlen line along a roughly two-kilometre section. As all three lines pass through the settlement area, the only option in this section is to install an underground cable.

Next steps

The next stage of the sectoral plan process is for Swissgrid to devise suggestions for corridors within the specified planning territory. After that, a monitoring group appointed by the SFOE will come together with the federal authorities, the affected cantons and environmental associations to discuss and assess the planning corridor variants developed by Swissgrid. The monitoring group’s recommendation then continues on to the public collaboration stage. The Federal Council is expected to define the planning corridor with a specific transmission technology (overhead line, underground cable or a combined solution) between Innertkirchen and Mettlen in autumn 2025. Ideally, the renewal of the Innertkirchen – Mettlen extra-high-voltage grid will be completed by 2035. After that, the existing line, parts of which run through the settlement area, will be removed.

Schedule in the best case without appeal to the courts
Schedule in the best case without appeal to the courts

Downloads


Additional information

  • Approval process

    Swissgrid is responsible for the project planning for and implementation of the transmission lines.

    Learn more

  • Emissions

    It is hard to imagine our daily life without the numerous electronic gadgets and tools. However, we are much less aware that electric and magnetic fields are formed everywhere electricity is present: including in the generation, transmission and distribution of electric energy.

    Learn more

  • Grid technologies

    The decision on whether to install a high-voltage line as an overhead line or as an underground cable is based on objective criteria. That's why Swissgrid checks the cable and overhead line options for every grid project.

    Learn more

Grid news

  • | Media release

    A new life for the power cables at the bottom of Lake Lugano

    Read article
  • | Media release

    Temporary voltage increase on the Bickigen – Chippis and Bassecourt – Mühleberg lines

    Read article
  • | Media release

    Groundbreaking ceremony for the new transformer at the Mettlen substation

    Read article

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.