Grid project Flumenthal – Froloo

Swissgrid is planning an extra-high-voltage line between the substations in Flumenthal (canton of Solothurn) and Froloo (municipality of Therwil, canton of Basel-Landschaft) in order to strengthen the supply of electricity in the greater Basel area and throughout the two Basel cantons. The new 220-kilovolt line will replace the existing 145-kilovolt line operated by IWB (Industrielle Werke Basel).


Your contact for this grid project

Sandra Bläuer
Sandra Bläuer

Phone +41 58 580 21 11
info@swissgrid.ch

Planning area
Planning area
Existing line
Existing line
Substation
Substation

Overview

  • The current 145-kV line operated by IWB (Industrielle Werke Basel) that runs between the Flumenthal and Froloo substations will be replaced by a 220-kV extra-high-voltage line operated by Swissgrid.
  • The new extra-high-voltage line between Flumenthal and Froloo is important to ensure a secure supply of electricity in the greater Basel area and throughout the two Basel cantons. The region is currently only supplied by the transmission grid from Bassecourt (canton of Jura) and Froloo (canton of Basel-Landschaft) onwards. The new 220-kV connection will improve redundancy in the Swiss transmission grid.
  • At the beginning of April 2022, Swissgrid submitted an application to the Swiss Federal Office of Energy (SFOE) to initiate the sectoral planning process.
  • The planning area stretches from Flumenthal (canton of Solothurn) north over the Weissenstein and Schelten mountains to the Laufen basin as far as the substation in Brislach (Laufen district, canton of Basel-Landschaft), which will be connected to the new line. The line will continue from the substation in Brislach via the Blauen mountain range to Therwil (canton of Basel-Landschaft), the municipality where the Froloo substation is located.
  • Swissgrid developed various corridor variants within the planning area. These variants were evaluated by a monitoring group made up of various technical experts appointed by the SFOE. Three corridors were examined in depth: an overhead line corridor, a partial underground cable corridor and a total underground cable corridor.
  • The monitoring group recommends the «overhead line» corridor. Before the corridor and the technology are defined by the Federal Council, private individuals are free to give their views on the monitoring group’s recommendation during the consultation and participation procedure.
  • The Federal Council is expected to determine the corridor for the new 220-kV line between Flumenthal and Froloo by the end of 2025. Swissgrid will then establish the specific construction project and submit the planning approval application to the competent authority, the Swiss Federal Inspectorate for Heavy Current Installations (ESTI). This will be followed by the public disclosure of the project. In the best-case scenario, provided there are no legal proceedings, Swissgrid will begin the construction of the line in 2030, and the work will take around two years.
  • Once the new line has been commissioned, the existing IWB 145-kV line will be dismantled, which will significantly reduce the impact on residential areas.

Project

The current line between the Flumenthal and Froloo substations is in operation as a two-strand 145-kV line. It is part of the national distribution system. The IWB line, which is around 33 kilometres long, has to be replaced due to its age. At the same time, the operating voltage on one of the strands will be increased to 220 kilovolts. This means that the line will be part of the Swiss transmission grid in the future and, as such, will be operated by Swissgrid. The second strand on the line, which will have an operating voltage of 145 kilovolts, will continue to be operated by the relevant distribution system operators as before.

The extra-high-voltage line between Flumenthal and Froloo will ensure electricity supply redundancy in the greater Basel area and strengthen security of supply across Switzerland in the long term.

Why the project is so important

A key aspect of this project is grid redundancy; the Froloo substation plays a key role in supplying the greater Basel area. Today, it is connected to the transmission grid in the stub, i.e. via a single line. If this line fails, electricity will no longer flow to the substation, which would substantially weaken supply in the region. Distributing the electricity flows along several north-south axes instead of just a few or a single one, as is the case today, will increase the security of supply in the region and, in the long term, the grid stability of Switzerland as a whole.

The current power line between Flumenthal and Therwil runs over the Rüttelhorn mountain.
The current power line between Flumenthal and Therwil runs over the Rüttelhorn mountain.

The planning area

At the beginning of April 2022, Swissgrid submitted an application to the Swiss Federal Office of Energy to initiate the sectoral planning process. The sectoral plan for transmission lines (SÜL) is the Swiss government’s superordinate planning and coordination tool for the construction and expansion of transmission lines.

The planning area stretches from Flumenthal (canton of Solothurn) north over the Weissenstein and Schelten mountains to the Laufen basin as far as the substation in Brislach (Laufen district, canton of Basel-Landschaft), which will be connected to the new line. The line will continue from the substation in Brislach via the Blauen mountain range to Therwil (canton of Basel-Landschaft), the municipality where the Froloo substation is located.

Swissgrid developed various working corridors within this planning area.

1/4
2/4
3/4
4/4

Corridor recommended by the monitoring group

In accordance with the sectoral plan for transmission lines (SÜL), a monitoring group consisting of various technical experts appointed by the SFOE assessed the variants for the planning corridor put forward by Swissgrid. Three corridors were examined in depth within the planning area: an overhead line corridor, a partial underground cable corridor and a total underground cable corridor. The monitoring group recommends the overhead line corridor.

  • Overhead line corridor
    The corridor for the overhead line is the corridor selected for final evaluation. Its position will ensure that the villages in the area are affected as little as possible and residential areas are avoided. During the next planning stages, care will have to be taken to ensure that the line route preserves the landscape as much as possible, taking particular account of groundwater protection and the interests of regional development. The dismantling of the existing 145-kV line, which runs close to the villages in some places, will significantly reduce the impact on residential areas, particularly at the southern foot of the Jura and in the Laufen basin, and the landscape will be restored.
  • Partial underground cable corridor
    In the partial underground cable corridor variant, the suggestion was to lay an underground cable from the Froloo substation to the Rütene district near Ettingen. The line would then essentially have continued along the currently planned route as an overhead line as far as the Flumenthal substation. This solution had to be rejected, as the cable conduit block needed for the cable would have encroached too much on ecologically and agriculturally valuable soil. These disadvantages would have been offset by comparatively minor advantages in terms of landscape protection.
  • Total underground cable corridor
    A total underground cable corridor was also analysed. This would have consisted of an underground cable from one substation to the other. This solution could not be pursued either. Interventions in the ground would have been required for the construction of conduit blocks and the excavation of tunnels by mining. This would have been extremely problematic, particularly with regard to groundwater protection. Another factor that contributed to the decision was the fact that even without opting for an underground cable, objects protected at both national and cantonal level, such as historic transport routes, could largely be preserved thanks to careful line routing. A cable line therefore did not seem absolutely necessary from the point of view of nature, landscape and heritage protection. In addition, there were serious technical arguments against an underground cable. Ultimately, a cable line would have been much more expensive than an overhead line.
Overhead line corridor monitoring group
Corridor recommended by the monitoring group

The SFOE monitoring group submitted a recommendation to the Federal Council in favour of the overhead line corridor shown on the map. The working corridor put forward by Swissgrid in the SÜL application was optimised following an on-site inspection and various technical discussions.

Technical difficulties caused by cables

Recent studies have expressed fundamental reservations about the use of long sections of underground cable in the extra-high-voltage grid for technical and operational reasons. On the one hand, long cable lines lead to undesirable reactive power compensation. On the other hand, cable systems can generate resonances that can disrupt or even seriously jeopardise stable grid operation. What is more, cable lines in the extra-high-voltage grid are also a hindrance when it comes to black start capability – i.e. the ability to restart the grid autonomously from a switched-off state. The operational risks increase for Swissgrid when there is a greater density of underground cables in the extra-high-voltage grid. In the future, it will only be possible to plan underground cables in the transmission grid where they are absolutely necessary. There is clearly no such need in the Flumenthal – Froloo project.

Public participation

Before the Federal Council makes its decision, private individuals are free to give their views on the monitoring group’s recommendation during the consultation and participation procedure.

The project documents will be available from the relevant municipal administrations for 30 days from 2 May 2025. During this period, private individuals can take advantage of the public participation procedure and contact the canton they live in:

  • Amt für Raumplanung des Kantons Basel-Landschaft
    Kreuzbodenweg 2
    4410 Liestal
    raumplanung@bl.ch
  • Amt für Gemeinden und Raumordnung des Kantons Bern
    Abteilung Kantonsplanung
    Nydegggasse 11/13
    3011 Bern
    kpl.agr@be.ch
  • Amt für Raumplanung des Kantons Solothurn
    Werkhofstrasse 59
    4509 Solothurn
    arp@bd.so.ch

The project documents can also be consulted on the SFOE website during the above-mentioned period.

Next steps

The Federal Council is expected to choose the corridor for the new 220-kV line by the end of 2025. Swissgrid will then prepare the construction project and submit the planning approval application to the competent authority, the Swiss Federal Inspectorate for Heavy Current Installations (ESTI). This will be followed by another public consultation. In the best-case scenario, provided there are no legal proceedings, Swissgrid will begin the construction of the line in 2030, and the work will take around two years. Once the new line has been commissioned, the existing 145-kV IWB line will be dismantled.

The following schedule is based on the current planning status and represents the best possible scenario, without taking into account potential legal proceedings.

Start of sectoral plan for transmission lines (SÜL)April 2022
Participation procedureMay 2025
Federal Council decision on corridor and technologyEnd of 2025
Development of construction project2026-2027
Planning approval procedure2028-2029
Construction of the new 220-kV line2030-2032
Dismantling of the existing 145-kV line2033

Dismantling of the old line

The existing 145-kV line runs close to the villages in some places. When planning the new 220-kV line, Swissgrid is taking care to ensure that the line is routed in a way that protects the landscape and residential areas as much as possible. Once the new line has been commissioned, the existing 145-kV line will be dismantled. This will considerably reduce the impact on residential areas, especially at the southern foot of the Jura and near the Laufen basin.

1/2
2/2

Downloads


Additional information

  • Approval process

    Swissgrid is responsible for the project planning for and implementation of the transmission lines.

    Learn more

  • Emissions

    It is hard to imagine our daily life without the numerous electronic gadgets and tools. However, we are much less aware that electric and magnetic fields are formed everywhere electricity is present: including in the generation, transmission and distribution of electric energy.

    Learn more

  • Grid technologies

    The decision on whether to install a high-voltage line as an overhead line or as an underground cable is based on objective criteria. That's why Swissgrid checks the cable and overhead line options for every grid project.

    Learn more

Grid news

  • | Media release

    A new life for the power cables at the bottom of Lake Lugano

    Read article
  • | Media release

    Temporary voltage increase on the Bickigen – Chippis and Bassecourt – Mühleberg lines

    Read article
  • | Media release

    Groundbreaking ceremony for the new transformer at the Mettlen substation

    Read article

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.